August 12th, 2019
Dolphins!
- drywall done
- Ceiling re-installed
- Painting done today
- Tiling in washrooms underway
- Millwork, plumbing and fixtures next week
- Hallway next week
- Our great custodians have the left side completed and cleaned as well as libary, office and staff room – they have worked very hard!
- Site foreman assures me they are on schedule for completion as discussed
- Both new portables on site and are being fitted with proper fixtures and utilities – waiting on inspections and landings